Liberia Bottled Water Project

A turn-key PET bottled water line delivered to Spoon Mineral Water Company, Liberia — from raw water treatment to film packing, commissioned in 2019 and running stably ever since.
Home Case Liberia Water Project

Bottled Water Production Line in Liberia

Location: Monrovia, Liberia, West Africa

Capacity: 6,000 bottles per hour (500ml PET)

Cooperation Year: 2019

Equipment Type: Water treatment, automatic bottle blowing, 3-in-1 monoblock filling, labeling and film packing

Project Background

Market Context

Liberia relies heavily on imported bottled water, and local production was held back by unstable power supply, high summer temperatures and limited after-sales resources. Safe, affordable locally-bottled water was in urgent demand after the national water supply recovery program.

Customer Needs

Spoon Mineral Water Company needed to expand from a semi-automatic workshop to a fully automatic line: increase capacity, upgrade quality consistency, realize turnkey delivery, and adapt the equipment to local voltage, water source and operator skill levels.

Our Solution

PROMAN delivered a complete line from raw water treatment, automatic bottle blow molding and the CGF16-16-6 rinsing-filling-capping monoblock to labeling and film packing — 6,000 BPH for 500ml PET bottles, with simplified PLC operation designed for first-time automatic line owners.

Equipment List of This Project

2000Bottles/hour

2000Bottles/hour

Entry model CGF8-8-3 monoblock for start-up bottled water plants.
View Details
4000Bottles/hour(HOT SALE)

4000Bottles/hour(HOT SALE)

Best-selling CGF14-14-5 line with PLC control and auto lubrication.
View Details
6000Bottles/hour

6000Bottles/hour

The exact CGF16-16-6 configuration delivered to this Liberia project.
View Details
8000Bottles/hour

8000Bottles/hour

CGF24-24-8 high-speed line for growing bottled water brands.
View Details

Project Execution

Line running video
Watch Video
01

Site Survey & Layout Design

Remote factory survey, workshop layout drawing and pipeline design matched to local utility conditions.
02

Installation & Commissioning

Two PROMAN engineers stayed on site for 45 days — installation, water and electricity connection, trial running and parameter tuning.
03

Operator Training

On-site training in simple English covering daily operation, maintenance and troubleshooting, with illustrated manuals left to the factory.
04

Long-term After-sales

7/24 online support, 48-hour spare parts dispatch, and regular follow-up visits by our West Africa service partners.

Project Results

6000 BPH
Stable output since 2019
40%
Production cost reduced
3
Neighboring markets covered
"The line has been running for years with very few problems. When we had questions, PROMAN engineers answered us online the same day. Our water is now sold across the country and even exported to neighboring countries."
— Manager, Spoon Mineral Water Company, Liberia

— FAQS —

Frequently Asked Questions

Do you have running references in my country?

PROMAN lines are running in more than 80 countries. Besides this Liberia project, we have references across West Africa, Southeast Asia, South America and the Middle East, and we can arrange video calls or factory visits with nearby customers.

What equipment types does a project like this include?

A typical turnkey bottled water project covers water treatment, bottle blowing, the rinsing-filling-capping monoblock, labeling, date coding, film packing and carton packing — each part can also be purchased separately to upgrade your existing line.

How long does delivery and installation take?

Production takes 30-45 working days after deposit, shipping about 30-40 days to West Africa. On-site installation and commissioning normally takes 30-45 days depending on workshop readiness.

Can the line run with local power and water conditions?

Yes. All motors and controls are configured to your local voltage and frequency, and we can add a generator-compatible design and extra buffer tanks for unstable water supply — exactly what we did for this Liberian project.

What capacity should I choose for a start-up plant?

Most new customers start from 2,000-4,000 BPH and upgrade later. The monoblock frame of this project allows future speed-up by adding filling valves, protecting your first investment.

How do I start a similar project?

Send us your bottle sample or target bottle size, capacity and water source report. Our engineers will reply with a layout drawing and quotation within 24 hours — the same process this Liberian customer started with in 2019.

Get Your Custom Liquid Packaging Solution

Tell us your product, capacity and bottle size — our engineers will reply with a professional proposal within 24 hours.

— LEAVE A MESSAGE —

Get in Touch With Us